Mobile Switching Center Upgrade

Location: Central PA

Client: Verizon Wireless

Value: $1 million

Precis Engineering led an in-house team of mechanical, electrical, and plumbing engineers and coordinated architecture and structural engineering consultants for upgrades to a mobile switching center. The project involved a control room renovation and additional workstations with ergonomic functionality. Key components of the project included:

  • Main electrical service upgrade with a new main utility transformer
  • A new lug box for a 1 megawatt mobile emergency generator
  • New sprinkler systems and a generator room micromist system
  • Early warning and very early warning fire detection systems
  • N+1 HVAC upgrades to telecommunications rooms
  • Seismic upgrades for overhead cable trays
  • Phased implementation for zero downtime